Energy Transfer Launches Appeals Following Court Order to Shut Down Dakota Access Pipeline

1-DSC09675
on

On Monday, July 6, a federal judge ordered the shutdown of the Dakota Access pipeline (DAPL) by August 5.ย Theย move followsย a March judgment that ordered the pipeline to undergo a more thorough environmentalย review.

However, Energy Transfer, the pipeline’s parent company, later revealed that the company was continuing to offer deals to oil companiesย to ship their product on DAPL during times when the pipeline is slated to be shut down. Today, the legal battle moved towards the U.S. Court of Appeals for the District of Columbia Circuit, after the judge denied a request to freeze the shutdownย order.

Energy Transfer said that it was continuing to offer shippers oil transportation on DAPL after the court-ordered shutdown date, Bloomberg reported on July 8, adding that the company had made โ€œno moves to take itย offline.โ€

โ€œWe are not shutting in the line,โ€ Energy Transfer spokeswoman Vicki Granado told Bloomberg, adding โ€œwe believe [Judge James Boasberg] exceeded his authority and does not have the jurisdiction to shut down the pipeline or stop the flow of crudeย oil.โ€

The company later clarified that it did not intend to defy courtย orders.

At a conference held today, โ€œDakota Access emphasized its understandable desire to be heard in the Court of Appeals as soon as possible,โ€ Judge Boasberg wrote. The parties, Judge Boasberg added, had agreed to negotiate over the details of shutdown logistics in theย meantime.

Dakota Access has already made one failed attempt to stall the shutdown order. Immediately after Monday’s shutdown order was issued, the company both appealed Judge Boasbergโ€™s decision and asked for a provisional stay of the shutdown. The Judge quickly rejected that request, citing the risk of spills and hazards posed by the pipelineโ€™s continuedย operations.

While the DAPL fight continues, a second major pipeline project in the U.S. was canceled and a third suffered a major legalย setback.

Dominion Energy and Duke Energy announced the cancelation of the Atlantic Coast pipeline, saying that the West Virginia-to-North Carolina natural gas project was โ€œtoo uncertain to justify investing more shareholderย capital.โ€

Andย the Supreme Court declined an emergency appeal that would have allowed the Keystone XL pipeline to resumeย construction.

‘Never Suggested’ Defiance, Energy Transfer Laterย Says

Energy Transfer’s statement that DAPL was not being shut down caused a stir, with some observers asking whether the company intended to openly defy the federalย court.

โ€œTo be clear, we have never suggested that we would defy a court order,โ€ the company wrote. โ€œRather, DAPL is seeking appropriate relief from that order through the established legalย process.โ€

Energy Transfer spokesperson Lisa Coleman said that, as a result, investors should not be concerned about the possibility of court sanctions against the company or itsย management.

The suggestion that the company might keep oil flowing unlawfully garnered immediate condemnation from Indigenous and environmentalย organizations.

โ€œPerhaps theyโ€™re taking their inspiration from the father of the Trail of Tears, Andrew Jackson. In response to the 1832 Supreme Court decision that established tribal sovereignty in the U.S. โ€” Worcester vs. Georgia โ€” President Jackson declared: ‘[Chief Justice] John Marshall has made his decision. Now let him enforce it,’โ€ the Lakota People’s Law Project, a Bismark-based legal advocacy group, wrote in aย statement.

โ€œBut this is not 1832,โ€ they continued. โ€œWe will not let this corporation, this pipeline, or this President trample on ourย sovereignty.โ€

Others observed that federal courts have a variety of ways to enforce their orders. โ€œEnergy Transfer is playing a very dangerous game,โ€ Jan Hasselman, an Earthjustice attorney who represents the Standing Rock Sioux Tribe, told Bloomberg. โ€œThey donโ€™t get to ignore a federal court order just because they disagree withย it.โ€

Over the last two decades, Energy Transfer has racked up a long record of unlawful acts and legalย violations.

Between 2000 and 2019, the company and its subsidiaries racked up $481,653,793 in fines, penalties, court-ordered actions, and other legal sanctions for breaching U.S. laws, according to a tracker published by corporate accountability nonprofit Good Jobs First. Of those 275 reported violations, 200 were related to environmental law-breaking, while others involved energy market manipulation, employment discrimination, False Claims Act-related offenses, and workplace safety issues, the Good Jobs First trackerย indicates.

In February, Energy Transferโ€™s Securities and Exchange Commission filings revealed that the company faces a federal criminal investigation into a 2018 gas pipeline explosion in Pennsylvania. The firm also faces a state-level investigation by Pennsylvania Attorney General Josh Shapiro over thatย incident.

Dakota Access pipeline and Bayou Bridge pipeline opponents outside of the US Army Corps of Engineers office in New Orleans
Protesters line the street in front of the U.S. Army Corp of Engineers headquarters in New Orleans, Louisiana, on Novemberย 15, 2016. Credit: ยฉ2016 Julieย Dermansky

The company has also pursued dubious legal strategies in the past. In February 2019, a federal court in North Dakota dismissed a $900 million lawsuit that Energy Transfer Equity, LP brought against Greenpeace International and other DAPL opponents. That lawsuit had alleged that DAPL opponents violated federal racketeering laws โ€” claims that were thrown out of federal court, with the company barred from raising themย again.

The company had also availed itself of tens of millions of dollarsโ€™ worth of law enforcement spending as it sought to build the Dakota Access pipeline, despite opposition from Indigenous-led water protectors and others at Standing Rock. Law enforcement costs topped $35 million during the pipeline dispute, and Energy Transfer had only defrayed $15 million of that tab, CBS News reported in Decemberย 2017.

Bakken Shaleย Slowdown

Itโ€™s not clear how much capacity on the Dakota Access pipeline Energy Transfer has continued to offer to shippers beyond the courtโ€™s deadline. Energy Transfer declined to specify how much of DAPLโ€™s capacity is currently under long-term contracts and how much space is available for last-minute walk-up customers. In 2016, an environmental assessment of DAPL indicated that just 10 percent of the pipelineโ€™s space was โ€œreserved for walk-up shippers,โ€ and 90 percentย was booked up under long-termย contracts.

DAPL has carried more than a third of the oil produced in North Dakota and Montana’sย Bakken shale region โ€” but the Bakken region has been hit by competition from the Permian shale in Texas and New Mexico, by plunging demand from the pandemic, and byย the shale industryโ€™s broader struggles to achieve profitability. After peaking at over 1.5 million barrels a day in 2019, North Dakotaโ€™s oil production has plummeted by 450,000 barrels per day as of July, as the oil drilling industry remains battered by low demand for itsย products.

A DAPL shutdown could also affect pipelines downstream from North Dakota, including the Bayou Bridge pipeline in Louisiana, which currently carries oil transported from North Dakota via Dakotaย Access.


Februaryย 8, 2017. Protests and disputes over the Dakota Access pipeline have continued across the U.S. for years. Credit: Steve Rapport, CC BYย 2.0

Before the shutdown order, Energy Transfer had been seeking to expand DAPL, despite the plunge in production. Last week, Reuters reported that Energy Transfer had deployed an unusual legal move to keep oil producers from backing out of contracts that underpinned a planned DAPL expansion. The company invoked force majeure, a legal provision often invoked to excuse non-performance because of an act of god or major catastrophe, to prevent shippers from abandoning theย pipeline.

โ€œHonestly, DAPL is not needed,โ€ Reuters quoted an anonymous DAPL expansion customer as saying. โ€œTheyโ€™re trying to build a house that all these people signed up for.ย Even if thereโ€™s no longer a need for the house, you canโ€™t really walk away from it. Would I like to get out? Yes, forย sure.โ€

In a declaration filed July 8, an Energy Transfer executive estimated that shutting down the pipeline could be done quickly, but emptying it out would take longer, requiring $24 million in expenditures to keep the pipeline in good condition during the 18-month process of completing its environmental review. Information about how much oil the company expected DAPL to carry in July was redacted from a public copy of thatย declaration.

Judge Boasberg’s July 6ย order had noted that the parties disputed just how significant the economic impact of a shutdown would be, observing that thousands of North Dakota oil wells had already been shut in for reasons that had nothing to do with DAPL.

He concluded that โ€œthe disruption Dakota Access focuses on is to its own interests and those of the industry, both of whom relied on the continued operation of the pipeline in the face of ongoing litigation as well as changes in the administrationโ€™s stance on the environmental propriety of theย pipeline.โ€

โ€œ[G]iven the seriousness of the Corpsโ€™ [environmental review] error, the impossibility of a simple fix, the fact that Dakota Access did assume much of its economic risk knowingly, and the potential harm each day the pipeline operates, the Court is forced to conclude that the flow of oil must cease,โ€ Boasbergย wrote.

Some industry analysts are already predicting that Energy Transfer is likely to prevailย on its appeal in the D.C. Circuit โ€” but other legal experts say that the DAPL shutdown order simply serves to reinforce the notion that the nation’s environmental laws haveย teeth.

โ€œI think what’s unusual,โ€ Elizabeth Klein, deputy director of the NYU School of Law’s State Energy and Environment Impact Center, told E&E News, โ€œis for the project proponent and the Corps to have gotten so far down the line knowing how risky it was to doย that.โ€

Main image:ย The Dakota Access pipeline under construction in South Dakota in 2016. Credit:ย Lars Plougmann,ย CC BYSAย 2.0

1-DSC09675
Sharon Kelly is an attorney and investigative reporter based in Pennsylvania. She was previously a senior correspondent at The Capitol Forum and, prior to that, she reported for The New York Times, The Guardian, The Nation, Earth Island Journal, and a variety of other print and online publications.

Related Posts

Analysis
on

Premier Danielle Smith can expect new tariffs, fewer revenue streams, and a provincial deficit brought on by lowered oil prices.

Premier Danielle Smith can expect new tariffs, fewer revenue streams, and a provincial deficit brought on by lowered oil prices.
on

Premier Danielle Smith declared sheโ€™s pursuing โ€˜every legal optionโ€™ in her fight against Trudeauโ€™s federal proposal to curb emissions.

Premier Danielle Smith declared sheโ€™s pursuing โ€˜every legal optionโ€™ in her fight against Trudeauโ€™s federal proposal to curb emissions.
on

Melinda Janki wants to protect her home country of Guyana from the harms caused by Big Oil.

Melinda Janki wants to protect her home country of Guyana from the harms caused by Big Oil.
on

Companies with major oil and gas interests have been given a stage at the UK pavilion in Baku.

Companies with major oil and gas interests have been given a stage at the UK pavilion in Baku.