Regulators Helped Oil-by-Rail Company Avoid Environmental Review, California Court Rules

mikulka color
on

This week, a court in California overturned a permit allowing the expansion of an oil-by-rail terminal near Bakersfield, California.ย The opinion from that court ruling reads like a case study for corporations looking to avoid the two biggest hurdles to getting such a project approved:ย environmental review and public notice andย comment.ย 

In 2012 Bakersfield Crude Terminal LLC (BCT) applied to the local air district for permission to build a facility that would allow up to two unit trains of oil per day to offload at its existingย terminal in Taft, California. According to this week’sย court document, the โ€œAir District is a public agency formed by eight counties and has jurisdiction over the San Joaquin Valley Air Basin, where it ‘ensures that proposed pollution sources comply with state [and federal] air qualityย regulations.’โ€

So, it was the job of the air district to review the proposed oil-by-rail project. In California, if a project or โ€œstationary sourceโ€ has a potential to emit 20,000 pounds or more of Volatile Organic Compounds (VOCs) per year, it qualifies as a major source of that pollutant. Once it passes that threshold, a project then requiresย the public be notified andย triggers the need for an environmental impactย report.ย 

According to the court documents, an engineer for the air district calculated that BCT‘s entire facilityย would have totalย emissions of 20,820 pounds per year, thus qualifying as a โ€œmajor source.โ€ However, the engineer then emailed a project manager at BCT and asked him to look for any โ€œdiscrepanciesโ€ in the calculations. However, the air district engineerย also โ€œsuggested ways to keep the proposal under the 20,000-pound per yearย threshold.โ€ย 

Not surprisingly, the project manager for BCT also had some ideas on how to do this and included the following in his responseย email:ย 

โ€œPlease rerun your numbers and let me know if those two things get us under the 20,000 lb threshold. We are trying to avoid Title V [major source permitting] at this time because [Bakersfield Crude Terminal LLC] feels the need to get the terminal built and establish themselves in the market ASAP.โ€ย 

The engineer did indeed rerun the numbers, and the new estimate came in under the 20,000 pound threshold. The project was then approved without further environmentalย review.ย 

The court documents also note that when Kern County, as the lead agency on the project, filed a notice of exemption from the California Environmental Quality Act (CEQA), โ€œThe only information in the notice possibly alerting the public that the proposed project involved the construction of a rail-to-pipeline transfer terminal handling crude oil was the name listed for the person carrying out the project, Bakersfield Crude Terminal LLC.โ€ย 

On that filing the project title was โ€œMinisterial Permit No. 2, Map No. 158.โ€ And the court documents also note that the filing failed to even provide a โ€œbrief description of the project.โ€ With so little information provided, there was little possibility for potential public outcry about โ€œMinisterial Permit No. 2, Map No. 158โ€ when it wasย proposed.ย 

And thanks to the engineer brainstorming with the corporate project manager on ways to make the numbers work, the project was listed as below the 20,000 pound pollutantย threshold. As a result, BCT was able to โ€œestablish themselves in the marketโ€ as the largest oil-by-rail facility in California with no environmentalย review.

At the same time this was happening in Bakersfield, two major oil-by-rail facilities were approved in Albany, New York, with no public opposition. While there was a public comment period, zero comments were made because the public was unaware of the proposals. Also around the same time in Washington state, three oil-by-rail terminals were approved with no public opposition, because as Terry Wechsler, an environmental attorney, explained to Reuters, โ€œThere was no opposition to the other three proposals only because we werenโ€™t aware they were in formalย permitting.โ€ย 

Air District Makes the Mathย Work

The recent court decision did not overturn the initial approval for the operation of the oil-by-rail facility inย Bakersfield.

Rather, the decision only coversย the planned expansion of the facility with the addition of a โ€œsewer systemโ€ that essentially was a way to capture oil and water runoff at the facility. The initial engineering review estimated the sewer system would create an additional 8,000 pounds of VOCs for the facility.ย When combined with the existing VOCs (that had been recalculated as just below 20,000 pounds),ย the facility comes in well over the 20,000 pound threshold,ย and โ€œpublic notification was required for the project.โ€ The court document explained what happenedย next.ย 

โ€œIn May 2014, Air District issued a public notice soliciting comments on the proposed issuance of authority to construct permits to Bakersfield Crude Terminal LLC for the sewer system. Comments from plaintiffs asserted Air District was required to prepare an environmental impact report on the terminal before permitting the sewer system because no prior CEQA review had beenย conducted.โ€

In August 2014, BCT withdrew its application for the project. Less than a month later, it reapplied with a proposal to have โ€œcarbon canister filtersโ€ on each of the four pumping stations. This would reduce the potential VOCs from 8,000 poundsย to only 500 pounds. An air district engineer reviewed the second application and determined that no environmental review would be required, even though the 500 pounds of VOCs still put the total project over the 20,000ย poundย threshold.ย 

There are another 30 pages of details in the court opinion, but essentially this is what happened next. First, the air district decided to split up the 500 pounds of VOCs across the system andย round down the smaller numbers to zero.ย The court opinionย explains:ย 

โ€œThen Air District applied the rounding policy to those daily figures, which rounded them down to zero and thereby treated the 509 pounds of annual VOC emissions as though it did notย exist.โ€

And if they didnโ€™t exist (in theory, at least), then โ€œthe facility would remain a nonmajor source of VOC emissions,โ€ and as a result, โ€œthe public notification requirements were notย triggered.โ€ย 

Rerun the numbers. Round down to zero. Get in the market ASAPย and keep the public in theย dark.ย 

Court Overturnsย Decision

But the court wasnโ€™t buying the math and, in short, made the followingย decisions:ย 

โ€œAir District’s assertion that it could be compelled to round down the emissions from each unit comprising the sewer system is clearly erroneous โ€ฆ We have determined that Air District’s decision that the proposed project is exempt from CEQA was wrong and must beย vacated.โ€ย 

Elizabeth Forsyth, the Earthjustice attorney who has been working on this lawsuit since it was filed in 2015, was quite happy with theย ruling.ย 

โ€œWe are pleased that the court recognized this blatant attempt to circumvent the environmental law California passed to protect communities,โ€ Forsyth said in a statement. โ€œAnd to allow them a voice in publicย decision-making.โ€

Main image: Oil trains Credit: Kurt Haubrich , CC BYNDย 2.0

mikulka color
Justin Mikulka is a research fellow at New Consensus. Prior to joining New Consensus in October 2021, Justin reported for DeSmog, where he began in 2014. Justin has a degree in Civil and Environmental Engineering from Cornell University.

Related Posts

on

Canadian environmentalist Tzeporah Berman makes the case for a "bold idea" to end the era of coal, oil and gas.

Canadian environmentalist Tzeporah Berman makes the case for a "bold idea" to end the era of coal, oil and gas.
on

High demand for wild-caught species to feed farmed salmon and other fish is taking nutritious food away from low-income communities in the Global South.

High demand for wild-caught species to feed farmed salmon and other fish is taking nutritious food away from low-income communities in the Global South.
Analysis
on

Premier Danielle Smith can expect new tariffs, fewer revenue streams, and a provincial deficit brought on by lowered oil prices.

Premier Danielle Smith can expect new tariffs, fewer revenue streams, and a provincial deficit brought on by lowered oil prices.
on

Jeremy Clarkson spreads well-worn conspiracy theory that casts inheritance farm tax policy as plot to โ€œreplace farmers with migrantsโ€.

Jeremy Clarkson spreads well-worn conspiracy theory that casts inheritance farm tax policy as plot to โ€œreplace farmers with migrantsโ€.