Following Lawsuit, Formosa Agrees to Hold Major Construction on One of Largest Planned US Plastics Plants Until 2021

picture-25834-1449425742.jpg
on
Sharon Lavigne speaking at the 2020 Juneteenth ceremony at the site of a former burial ground for enslaved African Americans on the site where Formosa plans to build a petrochemical complex. Credit: Julie Dermansky.

Back in late March, Formosa Plastics broke ground on its $9.4 billion plastics and petrochemical project in St. James, Louisiana, which the company has dubbed the โ€œSunshineย Project.โ€

Today, the company agreed to limit its construction activities until early next year, under a legal agreement reached with several community and environmental organizations who had filed a lawsuit last week. Major construction activities at the site will not move forward until Februaryย 2021 under the terms of todayโ€™s agreement, with the company required to provide monthly status reports including photographs of work underway andย completed.

In exchange, the plaintiffsย dropped their request for a preliminary injunction in the lawsuit, which claims that the U.S. Army Corps of Engineers had not adequately addressed numerous concerns over the petrochemical complex during the permit process, concerns which include air pollution, the impacts of flooding and hurricanes at the site, and the presence of graves where enslaved people had been buried on the grounds,ย a formerย plantation.

โ€œI feel elated,โ€ Sharon Lavigne, founder of RISE St. James and a St. James resident who has said her ancestors were buried on those grounds, told DeSmog. โ€œI have more faith than ever that we are going to stop Formosa.ย Even if they start building next year, we are going to stopย them.โ€ย 

The company agreed to defer โ€œconstruction-related activities for the permitted facility until no earlier than February 1, 2021, with the expectation of this Courtโ€™s decision on the merits of the Complaint by that date,โ€ according to court filings. The agreement specifically bars Formosa from building a dock on the Mississippi River and from working near wetlands or near five areas believed to contain the unmarkedย graves.

Plaintiffs in the lawsuit include the Center for Biological Diversity, RISE St. James, the Louisiana Bucket Brigade, and Healthyย Gulf.

โ€œNow that Formosa Plastics has agreed not to disturb graves and wetlands on the site through February 2021, we can focus on this projectโ€™s deeply flawed approval process,โ€ย Julie Teel Simmonds, a senior attorney with the Center for Biological Diversity,ย said in a statement. โ€œThis plant would sicken local residents, degrade wetlands, fuel climate change, and send plastic pollution into our rivers and oceans. It violates federal law and should never have beenย approved.โ€


Fence around the site of a suspected former slave burial ground in St. James on land Formosa bought to build its proposed $9.4 billion petrochemical complex. Credit:ย  Julie Dermansky for DeSmog.

The St. James Parish plant, one of several slated for the region, is planned to be a massive complex, with 14 units producing two types of plastic and the petrochemical ethylene glycol, which is used to make polyester fabrics andย antifreeze.

The projectโ€™s backers emphasized that โ€œpreconstruction activitiesโ€ would move forward under the terms of theย agreement.

โ€œThe agreement reached today allows plannedย preconstruction activities underway at the site to move forward,โ€ Janile Parks, Director of Community and Government Relations of FG LA LLC, a division of Taiwan-based Formosa Plastics Group, said in a statement sent to DeSmog. โ€œThese activities include the widening of Highway 3127, utilities relocations, soil testing, placement of test piles, and a pipeline removal. At the same time, plaintiffs agreed to dismiss their motion for preliminary injunction and established an orderly schedule for resolution of the pendingย lawsuit.โ€

โ€œFG will always be respectful of the burial remains discovered on its property,โ€ sheย added.

A second spokesperson told DeSmog that the agreement did not require delays to the project’s schedule. โ€œIn fact, we had already moved work on the construction dock to a later schedule,โ€ spokesperson Jim Harris said in anย email.

Simmonds, the Center for Biological Diversity attorney, noted that the dock schedule had been changed after the filing of the lawsuit. She also said that today’s agreement offered assurances that the company could not add construction activities between now and February. โ€œWe had no guarantee that that was all they were going to do,โ€ she told DeSmog. โ€œNow weโ€™ve got it in writing, so that makes a big difference toย us.โ€

The agreement comes at a time when petrochemical megaprojects nationwide are under increasing scrutiny from investors and financial analysts. โ€œConverting ethane to ethylene is still profitable,ย says Alan Gelder of Wood Mackenzie, an energy-research firm, โ€˜just not as profitable as some hoped,โ€™โ€ the Economist reported in June. In July, South Korean chemical giant Daelim announced that it was withdrawing from PTT Global Chemicalโ€™s proposed petrochemical complex on the Ohio River in Appalachia, and PTT has repeatedly delayed a final investment decision for theย project.

The ongoing pandemic has also made work on megaprojects significantly more difficult. In July, Shell officials said that 17 workers at its petrochemical plant in Beaver County, Pennsylvania, had tested positive for COVID-19 โ€” up from six workers as of June. The company had sent 96 percent of its workforce home during the early days of the pandemic, but then slowly ramped up construction activities after attempting to make the site more safe. โ€œWe’ve decided to at least temporarily halt the addition of workers,โ€ Shell spokesperson Michael Marr said lastย week.


Sign at the entrance to site where Formosa plans to build its petrochemical complex. Credit: ย Julie Dermansky forย DeSmog

The Department of Energy under President Trumpย has continued to push for a petrochemical โ€œrenaissance,โ€ releasing a report in early July that touted the Appalachian Basin’s low-cost shaleย gas.

In January, a report by the Environmental Integrity Project (EIP) found that planned petrochemical construction projects across the U.S., including liquefied natural gas (LNG) projects,ย would unleash hundreds of millions of tons a year of greenhouse gases, on par with building 50 new coal-fired powerย plants.

Formosaโ€™s St. James petrochemical project, the report found, had the potential to emit up to 13.6 million tons of greenhouse gasesย a year โ€” bringingย that plastics projectย to the top of EIPโ€™s list of potential newย polluters.

โ€œFormosa would be one of the largest plastics plants on the continent, and the Army Corps failed to give this project the scrutiny it deserves,โ€ Anne Rolfes of the Louisiana Bucket Brigade, also one of the plaintiffs in the case, said in a statement. โ€œWe will not allow St. James Parish to be destroyed for the sole purpose of enriching a company fromย Taiwan.โ€

Main image: Sharon Lavigne speaking at the Juneteenth ceremony at the locationย of a former burial ground for enslaved African Americans on the siteย where Formosa plans to build a petrochemical complex. Credit: ย Julie Dermanskyย forย DeSmog.

Related Posts

on

Immad Ahmed explains how "human-centered design" is helping displaced people in South Sudan and Bangladesh overcome daunting odds.

Immad Ahmed explains how "human-centered design" is helping displaced people in South Sudan and Bangladesh overcome daunting odds.
on

Unique collaboration convenes leaders from the global climate and trauma healing movements to explore the neglected inner dimensions of the crisis.

Unique collaboration convenes leaders from the global climate and trauma healing movements to explore the neglected inner dimensions of the crisis.
on

Corporations have found ways to be heard during negotiations on reversing the drastic global decline in plant and animal life.

Corporations have found ways to be heard during negotiations on reversing the drastic global decline in plant and animal life.
on

A 1961 oil and gas well is the suspected source of a geyser eruption in the region where Permian wastewater disposal is causing a flurry of earthquakes.

A 1961 oil and gas well is the suspected source of a geyser eruption in the region where Permian wastewater disposal is causing a flurry of earthquakes.