Roughly four years ago, Energy Transfer Partners (ETP) filed a federal application to build a 1,172 mile oil pipeline from North Dakotaโs Bakken shale across the U.S. to Illinois at a projected cost of $3.8ย billion.
Before that application was filed, on Septemberย 30, 2014, the Standing Rock Sioux Tribe met with ETP to express concerns about the Dakota Access pipeline (DAPL) and fears of water contamination. Though the company, now known as Energy Transfer, had re-routed a river crossing to protect the state capital of Bismarck against oil spills, it apparently turned a deaf ear to the Tribeโsย objections.
Following that approach proved to be a very costly decision, a new analysis concludes, with ETP, banks, and investors taking billions in losses as aย result.
โThis case study estimates that the costs incurred by ETP and other firms with ownership stake in DAPL for the entire project are not less than $7.5 billion, but could be higher depending on the terms of confidential contracts,โ a new report, โSocial Cost and Material Loss: The Dakota Access Pipeline,โ concludes, noting that represented nearly double the initial project cost. โThe banks that financed DAPL incurred an additional $4.4 billion in costs in the form of account closures, not including costs related to reputationalย damage.โ
In addition, the companyโs โpoor social risk managementโ caused taxpayers and โother local stakeholdersโ to incur at least $38 million in costs, the reportย concludes.
โThis is what it’s all about,โ protestor says. โSacred water.โ Not sure guys on left agree. #NoDAPL #DAPL pic.twitter.com/vHPRC2OHU5
โ Wes Enzinna (@wesenzinna) October 27, 2016
As opposition to DAPL grew from a handful of locals to a movement attracting thousands of supporters to Standing Rock and backers worldwide, construction fell behind schedule and over-budget, with costs rising from a predicted $3.8 billion to at least $7.5 billion, the new report finds. Over that time, Energy Transferโs stock price fell 20 percent โ at the same time as the tech investment index S&P 500 grew roughly 35 percent, the report noted. Energy Transferโs stock also underperformed other companies in the sameย industry.
โAcross the board, this project was out of line with the existing principles outlined in the United Nations Declaration on the Rights of Indigenous Peoples and other international standards for resource development near indigenous peoplesโ lands,โ Carla F. Fredericks, author of the study and director of Colorado Lawโs American Indian Law Clinic, said. โThe losses in this study underline that companies need to take those principles intoย account.โย
Making a ‘Materialย Loss’
The study points to early decisions by ETP as the cause of thoseย losses.
โThe Standing Rock Sioux Tribe communicated their opposition to DAPL for three years and they were frustrated by the lack of meaningful consultation from Energy Transfer Partners (ETP), DAPLโs parent company, and the U.S. Army Corps of Engineers (USACE),โ Fredericks, anย enrolled citizen of the Mandan, Hidatsa, and Arikara Nation of North Dakota, and co-author Mark Meaney of the University of Coloradoโs Leeds School of Business wrote. โIn fact, those opportunities for early engagement were ETPโs, the USACEโs and other investorsโ missed opportunities to understand the developing social risks that subsequently manifested into intense social conflict and ultimately resulted in materialย loss.โ
US / indigenous rights: @UNSR_VickyTauli urges consistent policies for projects like Dakota Access Pipeline https://t.co/fVdVZtcsnG
โ UN Human Rights (@UNHumanRights) March 3, 2017
When it comes to human rights issues, the reportโs authors dismiss the notion that a companyโs management can adequately protect shareholders from losses or liability if they use compliance with state and federal laws as their onlyย benchmark.
โUnfortunately, the companies and financiers behind DAPL presumed that compliance with national laws was sufficient for the project to move forward on Sioux territory rather than abiding by international human rights standards,โ the report finds. โTheir lack of attention ultimately resulted in materialย loss.โ
The report faults Energy Transferโs management specifically for failing to discloseย risks of costly delays due to public opposition to investors at an earlierย stage.
Guerrilla street painting against fossil fuel pipeline investment outside Wells Fargo World Headquarters in San Francisco,ย November 6, 2017.ย Credit: Peg Hunter, CC BY–NCย 2.0
โIn this case, ETPโs reporting concerning the project was silent or exclusively positive until the publication of its third quarterly report on November 9, 2016, in which the company acknowledged that โprotests and legal actions against DAPL have caused construction delays and may further delay the completion of the pipeline project,โโ the report finds. โBy this time, social pressure had been mounting for months and there is evidence that the company knew of these risks long before they were disclosed toย investors.โ
โThe timeline shows that ETP made few good faith efforts to understand and integrate the Standing Rock Sioux Tribeโs concerns about the environmental, social, and cultural risks into their operations and that ETP did not disclose known risks to investors until a later date,โ it adds. โAs a result, investors were not aware of the potential for delays and it is possible that this resulted in the overvaluation of ETPโs stockย price.โ
It wasnโt only ETPโs investors that suffered an economic blow due to DAPL. Reported account closures at banks that funded the DAPL project totaled $4.4 billion, including 150,000 personal bank account closures worth $86.2 million, with the remainder coming from cityย divestments.
โIt is reasonable to suggest that the degree of public criticism directed towards banks โ relative to the size of the transaction โ was greater than expected and was underestimated during the banksโ own review of the projectโs viability,โ the reportย says.
Courtroomย Fights
DAPL is now flowing oil โ but legal battles continue. In early November, Energy Transfer announced that it would seek to expand DAPLโs capacity from 525,000 barrels per day to 570,000 barrels a day, spurred by growing oil production from North Dakotaโs Bakkenย shale.
The DAPL fight is far from over. Lawsuits and criminal prosecutions of pipeline opponents now include a federal class action filed by five plaintiffs against private security firm TigerSwan and state and county officials, alleging that the defendants violated plaintiffโs constitutional rights by closing public roads for prolonged periods in 2016 to 2017, part of an effort to quiet resistance to the DAPLย project.
As DeSmog previously reported, the lawsuit โalso allegedย that, beyond impeding access to sacred grounds for the self-proclaimed ‘Water Protectors’ โ the term also used by [plaintiffs’ attorneys] Smith-Drelich and Harcourt in their complaintย โ the blockade imposed by government and law enforcement did not impact those who lived in the area or employees ofย Energyย Transfer.โ
Separately, Sophia Wilansky, who was shot three times by rubber bullets and suffered severe arm and hand injuries from what she alleges was a police โflashbangโ grenade at Backwater Bridge on November 20, 2016, filed a lawsuit against Morton County law enforcement and other agencies this month. And over 700 criminal cases brought against the pipeline opponents known as water protectors have been processed, with NPR reporting that โ[m]any have had their charges reduced orย dismissed.โ
โHappiโ American Horse from the Sicangu Nation locked himself to equipment at a Dakota Access pipelineย constructionย site onย August 31, 2016. Credit:ย Desiree Kane,ย CC BYย 3.0
In November, the Standing Rock Sioux Tribe challenged the adequacy of the Army Corps of Engineersโ environmental review of DAPL, arguing that the Corpsโ assessment of the risks, particularly the risk of an oil spill in Lake Oahe, which is on Sioux land, fell short of required standards and disregarded technical information provided by the Tribe to theย Corps.
In July, federal judge Billy Roy Wilson partially dismissed a racketeering lawsuit that was initially filed in August 2017 by ETP against nonprofits Greenpeace and BankTrack, as well as the environmental movement EarthFirst! (as represented by the publishers of a magazine of a similarย name).
โWhile the complaint vaguely attempts to connect BankTrack to acts of โradical eco-terrorist,โ an international drug distribution and money laundering enterprise, and violations of the Patriot Act, BankTrackโs actual conduct in this case was allegedly writing a few letters to financial institutions and posting links to the letters on its website,โ Wilson wrote in a July ruling dismissing claims againstย BankTrack.
In August, after a ruling that EarthFirst! is an environmental movement too amorphous too be named to a lawsuit and that suing the magazine would be โfutile and possibly frivolous,โย ETP added five individual defendants to its lawsuit, including a Greenpeaceย staffer.
ETP is also involved in the construction of other controversial pipeline projects, like the Bayou Bridge pipeline in Louisiana and the Mariner East projects inย Pennsylvania.
A proposed new Bakken pipeline, dubbed the Liberty Pipeline, was recently announced by Phillips 66 and Bridger Pipeline LLC. That pipeline would move 350,000 barrels a day of fracked oil from the Bakken shale to Corpus Christi, Texas, near major exportย terminals.
The authors of the new report had advice for companies contemplating building new pipeline projects or investing inย them.
โThese losses show how important it is for companies to fully account for environmental, social, and governance risks before projects get going,โ Meaney said in a statement accompanying the report. โSocial risks are clearly overlooked in theย market.โย
Main image: Bank divestment protests in Philadelphia. Credit: ยฉย 2017 Lauraย EvangelistoSubscribe to our newsletter
Stay up to date with DeSmog news and alerts