Southern Co. is accused of fraudulently misrepresenting the prospects for its troubled โclean coalโ project in Kemper County, Mississippi in several legal filings thisย summer.
Southern announced in late July that it was shuttering the troubled โclean coalโ part of Kemper after construction ran years behind schedule and the company spent $7.5 billion on the 582 megawatt power plant โย over $5 billion more than it firstย projected.
In a lawsuit filed today, Brett Wingo, a former Southern Companyย engineer, alleges he warned the company’s top executives that it would not be possible to meet key construction deadlines. Management responded by retaliating against him, the complaint asserts, and Southern continued to assure investors and the public that Kemper’s schedule and budget targets would be met, then blamed unpredictable factors like the weather when those goals wereย missed.
Wingoโs claim that Southern misled investors by concealing construction-related problems drew national attention in a front page New York Timesย investigation last year. In January,ย the U.S. Occupational Safety and Health Administration (OSHA) concluded thatย Wingo had suffered a โcontinuing pattern of retaliatory treatmentโ and ordered Southern to reinstateย Wingo, but the company has refused, according to a statement accompanying the lawsuit. (The caseย is โBrettย Wingoย v. The Southern Company, et al.,โ Case No.ย 2:17-cv-01328-MHH inย the U.S. District Court for the Northern District ofย Alabama,ย Southernย Division.)
A second less-noticed legal filing with Mississippi state regulators accuses Southern of misrepresenting Kemper’s prospects right from the outset, before construction even began. Those claims center on Southern’s projections for what it would cost to operate and maintain the plant once it was up and running, which the filing asserts were so low they wereย โindefensibleโ.
In an email to DeSmog, Wingo seconds those claims, saying that he believes management knew back in 2012 that its โoperation and maintenanceโ (O&M) projections were off โย but kept the accurate numbers under wraps forย years.
โBy hiding the true O& M costs for so long, apparently since 2012 and likely longer, Fanning basically ensured shareholders would be forced to absorb $6 billion in losses,โย Wingo toldย DeSmog.
โIn 2012, sunk costs on Kemper were only around $1 billion and the natural gas part of the plant substantially complete. It would have been a perfect time to stop a runaway train from running off the end of the tracks,โ he added. โBut history shows, thatโs not what Fanning and Southern Company chose toย do.โ
Marketย Swings?
If you ask Tom Fanning, the CEO of Southern Co., what went wrong with his company’s attempt to build a โclean coalโ power plant in Kemper County, Mississippi, he’ll tell you Southern actually succeeded in building thatย plant.
โWe committed to build a clean coal facility that would have a carbon footprint equal to or less than natural gas,โ Fanning told Bloomberg News last Wednesday, the day that Southern announced it was taking a new $3.012 billion loss on the Kemper project. โWe fulfilled thatย commitment.โ
It just turned out the market changed,ย Fanningย argued.
โWe built the plant, but in the meantime, natural gas prices fell. At the time we started building the plant, natural gas prices were around $10 per million BTU [British thermal units]. Today they’re around $3 per million BTU,โ he explained. โAs a result, the project became uneconomic and our regulator in Mississippi issued some guidance that basically said that they would not allow recovery of thoseย costs.โ
What Fanning failed to mention was that when Kemper was first on the drawing board, it was supposed to cost $1.8 billion to build โ but after years of missed deadlines and budget overruns, the price tag for building Kemper had climbed more than $5 billion, to $7.5 billion, making Kemper the most expensive fossil fuel power plant ever built in the U.S.
Talking to Bloomberg Wednesday, Fanning also never mentioned the wordย โfraud.โ
That omission was notable, in part because company records, recorded conversations, and other materials provided to The New York Times last year by Wingo, a former Kemper engineer turned whistleblower, suggest that Southern’s top management may have deliberately deceived investors about Kemper’s prospects, claiming in public that they could meet targets that the company’s own managers said privately wereย impossible.
The documents โshow that the plantโs owners drastically understated the projectโs cost and timetable, and repeatedly tried to conceal problems as they emerged,โ The Timesย reported.
Last May, the Securities and Exchange Commission (SEC)ย launched an investigation into those concerns. Shareholder lawsuits and litigation from power customers concerned about higher electric billsย followed.
Southern Co.ย and its subsidiary Mississippi Power Co.ย have previously rejected Wingo’s allegations of wrong-doing and said that the companies’ย own investigations and one by โoutside counselโ found Wingo’s claims were without merit. A Southern Co. press representative had not responded to a request for comment on Wingo’s new lawsuit, nor to questions about O&M costs, as of pressย time.
State utilities regulators are currently negotiating with the company over exactly how much money power customers in Mississippi, whose population is roughly 40 percent people of color and hadย the highest poverty rate in the U.S. last year, will be asked to cough up to pay for Kemper. Southern has absorbed roughly $6 billion of the project’s costs as losses, as of its August 2ย earningsย call.
The second, new allegation of fraud suggests that Kemper may have been ill-conceived even if gas prices hadn’t dropped โ and even if construction costs were kept underย control.
โThis thing just had so many shortcomings that if the first thing didn’t kill it, the next one would have,โ Charles Grayson, an expert witness whose testimony on Kemper is cited in the legal filing,ย toldย DeSmog.
Related DeSmog content:ย ‘Clean Coal’ Officially Dead in Mississippi as Southern Company Battered by Kemperย Fallout
Buriedย Billions
โSouthern and Mississippi Power Company misled the Public Service Commission when they predicted that the plant’s annual Operations and Maintenance cost would be $50 million,โ allegedย a motion filed by Thomas A. Blanton, a long-time opponent of the project, on Juneย 19.
Last fall, Southern Co. revealed that the costs to operate and maintain the plant, known in the industry as O&M costs, would actually be over $200 million a year, the motion pointsย out.
โIn fact, the latest O&M numbers show that just staffing the plant with Southern Company personnel will cost well over $50 million per year,โ the motion says. โGiven that fact alone, the Company knew or should have known that presenting $50 million as a meaningful assessment of how much the plant would cost to run per year wasย indefensible.โ
The same people at Southern Co. who prepared the allegedly fraudulent construction cost estimates also prepared the O&M cost estimates, Wingo told PBS in an @Issue episode that aired Sept. 9,ย 2016.
โI don’t think the economics for this plant were ever true,โ Wingo, who was fired in February 2016 after raising concerns to top Southern management, said. โI don’t think they wereย real.โ
Wingo said that after he realized the O&M projections and the cost projections were prepared by the same individuals, he sat down and checked the O&M numbers himself โ and came back with numbers more than six times what Southern wasย projecting.
โIt was an absolute shocker to sit down and run the numbers,โ he wrote, describing how power bills would need to climb an average of more than $1,500 a year in one of the country’s lowest-income areas to cover those maintenance costs alone, if Kemper were used as a coal plant, โbut it wasย undeniable.โ
Wingo said in an email that he believes company managers were alerted to the problem back in 2012 โ four years before the company publicly revised its O&M estimates from an initial $50 million a year to over $200 million aย year.
โJust recently, I talked to a high level manager who I know, but whom I promised not to name, who told me that the O&M costs the company finally admitted to on October 3, 2016 had actually been calculated in 2012,โ Wingo said. โThis person, who I knew to be a good, effective and ethical manager, told me he saw the new O&M numbers inย 2012.โ
โHe told me that he knows these new O&M numbers were communicated up the chain of command to higher management,โ Wingo wrote, โbut not reported to the public or toย regulators.โ
Those annual O&M costs will add up over the decades when a power plant is in service, turning tens or hundreds of millions of dollars each year into billions of dollars total. This means that the O&M hikes could be at least as important as the company’s construction cost over-runs, close observers of the project say. But while the billions Southern poured into construction made national headlines, relatively little attention has been paid to the O&Mย estimates.
Kemper should be considered finished, Fanning said in last week’s earnings call, because Southern had โdemonstrated every major facetโ of the complex power plant. But the plant has never been able to fully operate commercially on coal and has been burning natural gasย instead.
Nonetheless, Kemper’s โclean coalโ equipment already needs some majorย maintenance.
On June 5, Southern revealed in an SEC filing that critical equipment for the coal-fired part of the plant had already sprung leaks. Fixing those leaks would also require ripping through a dense labyrinth of steel pipes, so that the malfunctioning equipment could be accessed, adding up to two years of additional work at a cost of $164ย million.
Devil in theย Details
The Energy Information Administration (EIA) is the federal agency charged with providing accurate and independent information about energy to the public โ but that can be especially challenging when dealing with new and emergingย technologies.
Jeff Rissman, head of modeling at Energy Innovation, which promotes clean energy, said that compared to the EIA‘s 2008 or 2009 figures on what a generic carbon capture project might cost to operate and maintain, $50 million a year wouldn’t have seemed too badly out ofย line.
โ$50 million is actually quite close to what EIA would have projected at the time the project was under development,โ heย said.
But Rissman also noted that Kemper used markedly different technology than the EIA‘s theoretical plants. For example, Kemper uses โgassificationโ technology instead of burning solid chunks of coal, included two gassifiers rather than the EIA‘s one, and captured a different percentage of carbon emissions โ all of which could have raised or lowered the expected priceย tag.
That lack of reliable independent data spurred Grayson, director of the Bigger Pie Forum, which advocates for fiscally conservative policies in Mississippi, to build his own detailed computer model of Kemper so he could check the company’s costs projections back inย 2012.
โWe had already suspected just from the size of the plant and that sort of thing, we had come to the conclusion that gee, this just wasn’t realistic,โ he said. His numbers kept on coming back a far cry from what Southern was tellingย regulators.
โThey just didn’t go together,โ Grayson said. โThe O&M was one of those things that from very early on, we were looking at it and saying you cannot maintain that kind of plant and that kind of equipment for thatย price.โ
And as Kemper’s overall price tag grew from less than $2 billion to more than $7 billion, the projections for maintenance costs seemed to lag. It wasn’t until last October that Kemper managers first told regulators that the plant’s O&M costs would be over a billion dollars in its first five yearsย online.
If Kemper ever does go into full service, Grayson said, his independent analysis concluded that the O&M costs could prove as high as $400 million or more a year โ roughly double Southern’s October projections and eight times as much as Southern Co. originallyย predicted.
Southern Co.’s spokesperson did not respond to questions from DeSmog aboutย Kemper.
The Securities and Exchange Commission also declined to comment on its Kemper-relatedย investigation.
Decisionsย Decisions
Back in 2010, Mississippi regulators had to choose between Kemper’s โclean coalโ promise or other options, like a regular natural gas powerย plant.
The new allegations call into question whether they got reliable information as they made thatย decision.
For example, in 2009, a Southern Co. official testified that Kemper’s O&M costs were expected to run between $50 million and $100 million, while an all-natural gas option, Plant Sweatt, was projected to cost $30 million to $50 million to run, the records show. That means there’s an overlap between the low cost estimate for Kemper โ which includes not one but two coal gassifiers, plus carbon capture equipment and a natural gas combined cycle power plant โ and the high cost estimate for the stand-alone natural gas combined cycle Plantย Sweatt.
โCertainly you have to ask yourself why Plant Sweatt and Kemper had an overlap,โ Graysonย said.
The next year, Southern Co. chose to use the lower $50 million estimate as it presented Mississippi regulators with the math comparing Kemper against other projects in a January 5, 2010 decisionย matrix.
A Southern Co. press representative failed to respond when asked by DeSmog about the company’s justification for presenting the low-end $50 millionย figure.
The company has previously denied that Wingo’s allegations of mismanagement and fraud had any merit. โThe investigations into Wingo’s concerns both reached the same conclusion โ that his concerns were unsubstantiated and not otherwise supported by the facts,โ the company said in a statement after The New York Times pieceย ran.
Michael Avenatti, a plaintiff’s attorney, who is suing the company on behalf of a group of Mississippi power customers, said that the O&M issue could proveย significant.
โThere’s no question that operation cost projections provided to the state would have been relevant to the original approval, and to any subsequent rate increase they were pushing for,โ Avenatti said. โI think it’s further evidence of the deception that went on here, which I think is criminal, quiteย honestly.โ
Spending Money to Makeย Money
Why would a company want to build a power plant that’s too expensive to run? Part of the answer, critics say, is the way that utilities like power companies areย regulated.
Because they are essentially regulated monopolies, the laws governing how utilities like power companies make money are different than most industries, as explained in aย ย 2015 Wall Street Journalย article titled โUtilities’ Profit Recipe: Spend More.โ
โ[U]tilities have another incentive for heavy spending; It actually boosts their bottom lines โ the result of a regulatory system that turns corporate accounting on its head,โ The Journal reported, explaining that as long as state-level regulators sign off on a project, regulated utilities get a fixed percentage of what they spend as aย profit.
If that fixed rate is 5 percent, then for every $100 that a utility company spends on approved construction, they can make a nearly guaranteed $5 inย profit.
That’s part of the reason that a big expensive project like Kemper would have been so attractive to Southern Co. even as the construction bill grew, according to projectย opponents.
โWithin reason, so they don’t get a disallowance for imprudence, the utilities like spending money,โ said David Schlissel, an energy consultant who testified for the Sierra Club against Kemper in 2009. โSpending increases their profit because their profits areย percentage-based.โ
Cleanย Coal?
Kemper was supposed to be an engineering feat, able to turn the world’s least efficient but most abundant form of coal, lignite coal, into a climate-friendly fuel. That’s โclimate friendlyโย as compared to the kind of coal-burning power plants upon which the U.S. has historically relied for the bulk of itsย electricity.
Lignite coal, which tends to be damp, would be turned into a synthetic gas, and then the carbon dioxide from burning that โsyn gasโ would be captured and sold to oil companies, whichย use that carbon dioxide (CO2) to help revitalize old oil wells. To save on transportation costs, the lignite at Kemper would come from a strip mine right on site, riding a massive conveyor belt up to theย plant.
To transport water, syn gas, natural gas, captured carbon, sulfuric acid, and other ingredients consumed or produced by the plant, the project includes nearly a million linear feet of piping. Sitting on 2,900 acres, Kempย required over 100,000 cubic yards of concrete, plus 40,000 tons of structural steel to build. It was designed with enough advanced technology that engineers describe it as more closely related to a chemical refinery than a standard coal powerย plant.
On July 6, Mississippi regulators issued an order that effectively put the brakes on Kemper’s coal project, signaling a start to settlement negotiations between the state and company and threatening to revoke Kemper’s permits ifย necessary.
Days later, Southern Co. announced that Kemper’s โclean coalโ experiment would be suspended. The power plant will run on natural gas, the company announced, and observers expect the โclean coalโ portion of the plant will beย mothballed.
Environmentalists have long objected toย calling a coal-fired carbon capture and sequestration project โclean coal,โ arguing that the label is misleading because it focuses on carbon dioxideย pollution while ignoring other problems like acid rain and airborne contaminants. And carbon capture projects rely on continuing fossil fuel production, because the CO2 that’s captured is sold to oil companies who pump it intoย aging wells to coax more oil from theย ground.
Politicians nevertheless continue to use the term. โMy administration is putting an end to the war on coal,โ President Donald Trump said this spring. โWeโre going to have clean coal, really cleanย coal.โ
Asked about the prospects for new โclean coalโ projects in general after Kemper’s shuttering, a top Department of Energy official was dubious. EIA chief Howard Gruenspecht noted the role of natural gas prices, as well as the lower price of oil, which hurts the price of carbon sold to enhance oilย recovery.
โIn some parts of the world, one could imagine perhaps some efforts there but the cost situation is very, very challenging, certainly in the United States,โ Gruenspecht told DeSmog. โOne does not have to have an issue with the technology itself, it’s very impressive, but it’s a question of whether things really pencil out or not โ there are some significantย challenges.โ
Main image: ย Southern Co. CEO Tom Fanning.ย Credit:ย ยฉย 2016ย Lauraย Evangelisto
Subscribe to our newsletter
Stay up to date with DeSmog news and alerts