TransCanada, the company currently constructing the southern segment of the Keystone XL pipeline, claims to use โtop quality steel and welding techniquesโ throughout its pipelineย network.ย
Last week, however, activists fighting the construction of the pipeline released images of what they claim are improperly welded pipeline seams. The photos were released by Keystone XL blockader Ramsey Sprague at the Pipe Tech Americas 2013 conference in Texas and were taken by blockader Isabelย Brooks.
Brooks took the photographs from inside a pipe segment on December 3, 2012 to document what they say was daylight pouring through weld seams between segments. โAll of us looked at it,โ Brooks told DeSmog, speaking of the defective seam, โand it was clear light was coming in from the outsideโฆIt was definitely clear what itย was.โ
An hour after the protesters were extracted from the pipe segment, says Brooks, it was in the ground. โ[Other protestors] told me that it was in the ground that day and buried. So they didn’t test it again,โ she said. โI know exactly the piece of pipe that it’s at, so if we were to dig it up I know it would be right there and as clear as thatย day.โ
These two images from inside the pipe were released by Sprague lastย week:
There are different types of weld marks, Brooks explained: โthere is a spiral weld on the inside and then there is a circumference weld that goes around each segment of pipeโฆat around 25 feet, along each segment of pipe, there is the weld that connects two piecesย flushly.โย
It was along the connecting seam between two segments of pipe that Brooks first noticed the outside light. โWe were sleeping for a while after we had locked ourselves inside of the pipe. I was about 25 feet in and we all knew this. We were tired and were waiting for the police to arrive and we settled down and tried to get some rest. I, at one point, woke up and it was dark insideโฆbut it was after sunrise and this circle of light became present aroundย me.โ
โI was right underneath it which is the bizarre part – that I just happened to lie down [and] it was right around meโฆand it was like little pokes, little dots all aroundโฆSome areas had more light coming through and some didn’t but it was a clear circle aroundย me.โ
โWhen I saw that I told Matt about it, another person who was with me, and I told Glen as well. We had a little conversation about it, [saying], ‘Wow. Crazy. Are you sure? That would be a really big thing, if that was theย case.โ
โI’m a photographer so I can speak to the lighting,โ said Brooks. โI turned the aperture up and turned the shutter speed down really lowโฆI know that it’s very ambiguous. It’s not the best image at all and if I had a camera that could have taken a better image it would have been preferable or even if the light was better because it was a foggy, overcastย day.โ
But still, said Brooks, โit was definitely clear what itย was.โย
โI just had to point and shoot and as anyone who saw images of the pipe it’s completely dark inside unless you use a flash but the flash wouldn’t have worked obviously because the light was coming in from theย outside.โ
Brooks, along with her two companions, Matt Almonte and Glen Collins, were arrested at the scene and spent 24 days in jail. During that time, Brooks was unsure of the fate of the image, which remained in policeย custody.ย
โI was sitting on the information for a while,โ she said, โbecause I didn’t want to put it out over the phone and I didn’t want to send hope to my friends [because] I didn’t know if the camera was going to make it through the jail system. I had planned on taking the memory card out and taking it with me but they took it from me and put it with my property. I was excited when I saw it andโฆI immediately flipped through and saw this image and said, ‘oh my god, here is it, here we go. This is the bigย thing.’โ
The images have reignited concerns over TransCanada’s poor safety practices exposed by companyย whistleblower Evan Vokes in Mayย 2012.
Vokes, a former TransCanada metallurgical engineer, said the company’s substandard practices and failure to meet welding regulations led him to file a formal complaint with Canada’s National Energy Board (NEB). Vokes was moved to report TransCanada’s non-compliance to the federal body after officials with the company refused to act on hisย complaints.
โI wrote a series of emails to a series of project managers saying, ‘We can’t do this practice, we can’t do this practice, we can’t do this practice,’โ Vokes told the CBC. โAnd I received increasingly pressured emails about how things were OK to do it thatย way.โ
TransCanada fired Vokes on May 8, 2012. Less than 6 months later, the NEB issued a public letter to TransCanada, stating โmany of the allegations of regulatory non-compliance identified by the complainant were verified by TransCanada’s internalย audit.โ
The NEB added it was โconcerned by TransCanada’s non-compliance with NEB regulations, as well as its own internal management systems andย procedures.โ
Vokes also observed a serious conflict of interest when TransCanada pipeline contractors hired their own pipeline inspectors, despite federal regulations making independent inspectionย mandatory.
โIn pipelining, there is a huge amount of stress for a very thin pipe,โ he told the CBC. โYou certainly should be paying attention to what is wrong with your pipe, making sure nothing happens to it, and there are no injurious defects to your pipe as it is being put into theย ground.โ
The current construction of the southern leg of the Keystone XL is being handled by Michels Pipeline Construction, a contractor forย TransCanada.ย
Isabel Brooks said Michels should be held responsible for the faulty seam. โWhomever does the welding of the northern half of the Gulf coast line, they are the ones who had this slip up. It was definitely something that was done on landโฆWhen they put this segment togther that’s where the issue comesย from.โ
Subscribe to our newsletter